The Commercial Thread

Connecting every commercial decision from customer enquiry to commissioning and financial close

I have lost count of the times I have explained this simple principle to varied stakeholders involved in the delivery of a construction project.

The Commercial Thread through the project lifecycle

StagePrincipal’s commercial objectiveKey methods / skillsCommercial Thread output
1. Enquiry / NeedUnderstand what the customer actually requires and whyRequirements definition, stakeholder management, scope developmentStatement of need
2. FeasibilityDetermine whether the project is technically, commercially and financially viableOption analysis, benchmarking, risk assessment, constructability, early estimatingPreferred option + feasibility estimate
3. Concept DesignDefine enough scope to establish a defensible cost and risk positionDesign management, value engineering, cost planning, schedule developmentConcept baseline
4. Cost PlanningUnderstand what the project should cost before asking the marketQuantity take-offs, first-principles estimating, benchmarking, escalation, contingency analysisPrincipal’s cost plan / estimate
5. Procurement StrategyDecide how the market should be engaged and where each risk should sitMarket analysis, packaging, risk allocation, contracting strategyProcurement and contracting strategy
6. Tender DocumentationEnsure the market prices exactly what the Principal intends to buyScope writing, specifications, drawings, BoQ/pricing schedules, commercial conditionsTender baseline
7. Tender EvaluationEstablish what each tenderer has actually priced and excludedTender normalisation, clarification, commercial/technical evaluation, risk pricingEvaluated tender position
8. Contract AwardConvert the tender into an enforceable commercial baselineContract drafting, scope reconciliation, departure closure, negotiationContract baseline
9. ConstructionEnsure expenditure remains consistent with contractual entitlement and approved scopeCost control, scheduling, forecasting, change control, claims management, contract administrationCurrent approved forecast
10. CommissioningProve the asset performs as contractedTesting, verification, defect management, completion certificationVerified operational asset
11. HandoverConfirm the Principal received what it paid forAsset records, as-builts, warranties, manuals, training, completion documentationAccepted asset
12. Commercial CloseEstablish the final contractual and financial positionFinal account, claims settlement, reconciliation, release of securitiesFinal commercial position
13. Lessons LearntFeed actual performance back into the next projectEstimate reconciliation, productivity analysis, benchmarking and lessons learnedBetter future estimates and contracts

At any point in the project lifecycle, can the project team clearly explain:

  • what is being delivered, and what it should cost;
  • what assumptions were made;
  • what risks the Principal carries;
  • what the contractor is obligated to deliver;
  • what has changed and why; and
  • what is the final outcome now expected to be.

If the answer is yes, the Commercial Thread is intact.

If the answer is no, the project may still appear to be progressing, but commercial control is already weakening or worse still, it has failed